Construction & Demolition Debris Management Program – Effective August 13, 2009

On July 14, 2009, the Board of Supervisors of Alameda County adopted Construction & Demolition Debris Management Program for unincorporated areas of Alameda County. Effective August 13, 2009, any covered projects submit for building permit applications will be subject to the Construction & Demolition Debris Management Program.

COVERED PROJECTS

  • Any project requiring a demolition permit;
  • Residential – Work Area more than 1,000 square feet;
  • Non-Residential – Work Area more than 3,000 square feet.

WASTE DIVERSION REQUIREMENTS

  • 75% of inert solids;
  • 50% of all other construction waste.

SUBMITTAL REQUIREMENTS

  • Building Permit Process: Submit Construction Debris Management Plan at time of building permit application for review and approval.
  • Inspection Process: During construction, contractor or permittee shall submit receipts from approved facilities for diversion of waste to the County building inspector for approval.